Audit Project
Audit Projects
How to check the quality of completed works and stump removals.
What is an audit project
An audit project is a special Inspection project used to check work that has already been completed. An auditor visits a sample of completed works (or stump removals), marks each one as Pass or Fail, and can send failed work back to be redone.
You can audit:
- Works projects: completed maintenance work such as pruning or tree removal.
- Stumps projects: completed stump removals.
Before you start
- The client account needs the Audit completed work permission. Without it, the "Audit this work" button does not appear. Contact Forestree support to enable it.
- The Works or Stumps project needs at least one completed item. Only completed work can be audited.
- Shared (partner) accounts can view a project but cannot create an audit project from it.
Create an audit project from a Works or Stumps project
- Open the Works or Stumps project and go to its project settings (the Update Project screen).
- Find the Works Audit Project section (or Stumps Audit Project).
- Enter the Percentage of Works to Audit. The default is 100%.
- Click Create Works Audit Project.
The system then:
- Creates a new project named "<project name> - Audit" covering the same area.
- Picks a random sample of the completed items using your percentage. At least one item is always included.
- Links the audit project to the original. The original project now shows an "Audit Project: <id>" button that opens it.
Note: Each project can have only one active audit project. To start again, remove the existing audit project. The original will then offer the create button again.
Note: The sample covers only items completed at the time you create the audit. Work completed later is not added automatically.
Create an audit project from the Works Analyser
Use this when you want to audit works across several projects, or works filtered by date, contractor, work type and so on.
- Open the Works Analyser in Reporting and set your filters.
- Click to create a project from the results.
- Tick Auditing Project.
- Enter the percentage of works to audit, then create the project.
A random sample of the filtered works is added to the new audit project. These audits are not linked to a single original project, so reworks are not added back to one.
Auditing a work
Map icons
When an audit project is open on the map, the Audit Project Legends panel shows what each icon means:
- Grey leaf: not audited yet.
- Green tick: passed.
- Red cross: failed.
Recording an audit
- Click a tree on the map to open its details, then open its history.
- Find the completed work and click Audit this work.
- Choose Pass or Fail.
- Optionally add audit notes (up to 500 characters). Notes are copied onto any rework.
- If you chose Fail, decide whether to switch on:
- Create Reworks? for works and tree removals
- Revert to Stump? for stump removals
- Click Save.
The work in the tree history then shows a "Passed audit" or "Failed audit" badge, with the notes, date and auditor's name.
Note: You can change a result later. The button then reads "Re-Audit this work".
What pass and fail do
- Pass: the result is recorded. Nothing else changes.
- Fail without reworks: the result is recorded so it shows in reports. No new work is created.
- Fail + Create Reworks (works): a new incomplete work item, tagged REWORKS, is created with the same tasks and the audit notes. If the audit was created from a Works project, the rework is added back to that Works project so the crew can redo it.
- Fail + Create Reworks (tree removal): the tree's removal is undone. A removed tree goes back to active, and a tree that became a stump goes back to a tree. A rework item is created.
- Fail + Revert to Stump (stump removal): the removed stump goes back to Stump status so it can be removed again. On the Stumps map it shows a rework icon, and its details show a "Failed Audit - Needs Rework" banner with the notes.
Tracking results
Open the project card and expand its details to see Audit Results:
- Passed: items that passed.
- Failed: items that failed.
- Reworks: failed items sent back for rework.
Progress on an audit project counts audited items, whatever the result. For example, 8 of 10 means eight items have a pass or fail recorded.
Works projects also show Audit Results, so you can check the quality of a project's works without opening the audit project.
Troubleshooting
- "No completed works found to audit." The project has no completed items yet. Complete at least one, then try again.
- The Create Audit Project button is greyed out. You are signed in to a shared (partner) account, or an audit project is already being created.
- There is no create button, only "Audit Project: <id>". This project already has an audit project. Use that one, or remove it to create a new one.
- "Audit this work" does not appear. The client needs the Audit completed work permission, and the work must be Complete.
- "Only completed works can be audited." The work was changed to incomplete before the audit was saved. Complete it first.
- A rework did not appear in the original Works project. Check that "Create Reworks?" was switched on, and that the audit was created from that Works project, not the Works Analyser.
- Some trees do not appear on the map. Open the side bar and enable 'Removed Trees' as by default trees that have been removed as part of work are not shown initially.